Rock Excavation – Construction Noise

Under Construction
Throughout the semester you will hear a lot of noise coming from the Post Learning Commons construction site.  Construction managers have done their best to keep the noise to a minimum, when possible. We understand that many of you come to the Library for quiet study, which is why construction managers have scheduled the loudest work to occur during our least busy times.

Excavation Schedule:

Starting Monday, January 24, 2011

(M-F) from 6am to 10am – hammering
(T and R) from 6am to 1pm – hammering
(M-F) rest of time – low hum noise

Spring Break – full time hammering
4/22 & 4/25 – full time hammering
Weekends – hammering only if contractors fall behind
Exam Week – They will go silent

We thank you for your patience during this process.